What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? PX ACTIVITY CRASH NORMAL TIME (DAYS) NORMAL COST CRASH COST IMMEDIATE PREDECESSOR(S) TIME (DAYS) A 6 5 $ 900 $1,000 B 8 6 300 400 C 4 3 500 600 – D 5 3 900 1,200 ? A E 00 5 1,000 1,600